Analisis Cost Varians (CV) dan Schedule Varians (SV) Pada Proyek Pembangunan Gedung UTD Kota Pasuruan Dengan Metode Earned Value

Setiyono, Agus (2020) Analisis Cost Varians (CV) dan Schedule Varians (SV) Pada Proyek Pembangunan Gedung UTD Kota Pasuruan Dengan Metode Earned Value. Masters thesis, Untag 1945 Surabaya.

[img] Text
COVER.pdf

Download (88kB)
[img] Text
DAFTAR ISI.pdf

Download (88kB)
[img] Text
DAFTAR PUSTAKA&LAMPIRAN.pdf

Download (234kB)
[img] Text
LEMBAR PENGESAHAN.pdf

Download (90kB)
[img] Text
Lembar Pernyataan Persetujuan Publikasi.pdf

Download (127kB)
[img] Text
Biodata.pdf

Download (73kB)
[img] Text
BAB I.pdf

Download (105kB)
[img] Text
BAB II.pdf

Download (261kB)
[img] Text
BAB III.pdf

Download (122kB)
[img] Text
BAB IV.pdf

Download (595kB)
[img] Text
BAB V.pdf

Download (81kB)

Abstract

In the construction work of UTD CityPasuruanBuiding owned by the Regional Government, with a Work Period of 90 Calendar Days (13 weeks). During the Implementation There was no significant physical progress, but on the contrary starting on the third week,it began to accur. successive delays up to the eighth week with late Progress reached 30% of the plan, or physical achievement of 49.48% of the Schedule of 79.570% (5 weeks remaining ). The purpose of writing this is to analyze the cost variant (CV) and schedule variant (SV) with Result Value Analysis (Earned Value Analysis) methode in evalualting time performance in an integrated manner, using indicators, namely, ACWP (actual cost of work performed), BCWP (budgeted cost of work performed), and BCWS (bugeted cost of work scheduled) Cost Varians (CV) = BCWP - ACWP and Schedule Varians (SV) = EV - PV or SV = BCWP - BCWS. The result of this study are to get the Cost Varians magnitude (CV) on the eighth weekRp. 1,074,426,838.48 Positive CV values indicate the costs incurred are lower than the planned budget, And the Amount of Schedule Variance (SV) Rp. - 760,823,295.39 Negative SV value show the timeof project implementation is too late from the initial planning, Meanwhile the TE (Time Estimate) time needed to complete the project is 8.06 Weeks.

Item Type: Thesis (Masters)
Uncontrolled Keywords: Earned Value Analysis, keterlambatan, Varian biaya
Subjects: T Technology > T Technology (General)
Divisions: Fakultas Teknik > Magister Teknik Sipil
Depositing User: Didik Ahmad
Date Deposited: 12 Dec 2020 22:15
Last Modified: 18 Jul 2022 07:00
URI: http://repository.untag-sby.ac.id/id/eprint/6743