Nurfianti, Rizkya Angelita (2020) Analisis Waktu Dan Biaya Pembangunan Hotel Solia Boutique Solo Laweyan Dengan Metode Critical Path Method. Undergraduate thesis, Universitas 17 Agustus 1945 Surabaya.
|
Text
ABSTRAK.pdf Download (580kB) | Preview |
|
|
Text
Bab 1.pdf Restricted to Repository staff only Download (98kB) |
||
|
Text
Bab 2.pdf Restricted to Repository staff only Download (261kB) |
||
|
Text
Bab 3.pdf Restricted to Repository staff only Download (177kB) |
||
|
Text
Bab 4.pdf Restricted to Repository staff only Download (934kB) |
||
|
Text
Bab 5.pdf Restricted to Repository staff only Download (37kB) |
||
|
Text
13.-Daftar-Pustaka.pdf Download (256kB) | Preview |
|
|
Text
LAMPIRAN.pdf Download (2MB) | Preview |
|
|
Text
JURNAL.pdf Download (625kB) | Preview |
|
|
Text
TURNITIN ANALISIS WAKTU DAN BIAYA PROYEK PEMBANGUNAN HOTEL SOLIA BOUTIQUE SOLO LAWEYAN DENGAN METODE CRITICAL PATH METHOD(2).pdf Download (1MB) | Preview |
Abstract
analisis waktu dan biaya pembangunan hotel solia boutique solo laweyan dengan metode critical path method
| Item Type: | Thesis (Undergraduate) |
|---|---|
| Subjects: | E History America > E11 America (General) E History America > E151 United States (General) |
| Divisions: | Fakultas Teknik > Program Studi Teknik Sipil |
| Depositing User: | Rizkya Angelita Nurfianti |
| Date Deposited: | 06 Aug 2020 05:59 |
| Last Modified: | 18 Jul 2022 05:38 |
| URI: | http://repository.untag-sby.ac.id/id/eprint/4287 |
Actions (login required)
![]() |
View Item |